TL;DR
- Sheikh Hamdan bin Mohammed, Crown Prince of Dubai, announced on 26 November the award of further Al Maktoum International Airport contracts worth about AED 56.5bn ($15.4bn), according to the Dubai Media Office.
- Together with about AED 23.8bn awarded earlier, the total awarded to date is about AED 80bn, the same release says.
- The new packages cover foundations for the West Terminal and two concourses, the superstructure of Concourses 2 and 3, and two 132/11 kV substations; the first phase is due to open in 2032 (The National).
Dubai has put another large block of money behind its second airport. The newly awarded contracts are worth more than twice everything awarded before them, and they move the project from groundworks towards buildings. The release does not name the contractors.
What did Dubai award?
New contracts worth about AED 56.5bn, announced on 26 November by Sheikh Hamdan bin Mohammed (Dubai Media Office). The National converts the figure to $15.38bn, and Gulf News and Khaleej Times both report the total awarded for the project as more than AED 80bn.
In the preceding phase, Dubai Aviation Engineering Projects awarded packages worth about AED 23.8bn for enabling works, substructure, the automated people mover and baggage handling (Dubai Media Office).
Contracts awarded for Al Maktoum International Airport (AED bn)
What is in the new packages?
Four blocks of work, listed in the Dubai Media Office release:
- West Terminal Building and Concourse 1: substructure, basements, tunnels, short-term car parks and the Ground Transportation Centre, with metro interface works.
- Concourse 4: substructure and underground infrastructure.
- Concourses 2 and 3:
- superstructure
- large-span steel roof spaceframes
- façades and roofing
- fit-out and building systems
- Power: two principal 132/11 kV substations with associated cabling.
The release says enabling works at Concourses 2 and 3 and the central area are nearing completion, with more than 24.23 million cubic metres excavated and 7,635 piles done. It puts the workforce across the Concourse 2 and 3 substructure packages at about 14,000 people (Dubai Media Office), the number Sheikh Hamdan also cited in his post on X (Gulf News).
How does it fit the timetable?
Dubai Airports' chief executive Paul Griffiths said on 17 November that the first phase is due to open in 2032 and that there will be at least a year of testing before the first passenger arrives. He added that the airports will run in parallel at first (The National). The first phase is expected to have capacity for 150 million passengers a year, and the full build more than 260 million (The National).
In August, Griffiths said a further AED 55bn of contracts would be awarded by the end of 2026 (The National). The announced AED 56.5bn is slightly above that figure, and it arrives with five weeks of the year left. The National also reports that construction has continued at full pace despite the Iran war (The National).
The site workforce figures differ by scope. Griffiths put the number on site at more than 100,000 on 17 November (The National), while the 14,000 in the release refers only to the Concourse 2 and 3 substructure packages.
Why it matters
Our view: this is a timetable commitment as much as a spending one. If the contracts hold to the approved programme, then the 2032 opening and the year of testing before it set the date by which Dubai South land, housing and logistics space around the airport has to be ready for demand.
If the AED 80bn awarded so far is only part of a project that The National values at $35bn, then further awards will follow, and each will tell us how fast the programme is moving. The scale is also why the release calls the project "a strategic investment in Dubai's future" (Dubai Media Office).